Singapore’s larger building projects need a new approvals plan
Since 1 October, new projects of at least 5,000 square metres have entered Singapore’s CORENET X submission process; some ongoing projects can stay on the earlier route. Project teams need to settle which path applies before planning their handovers.

Singapore is moving larger new projects onto CORENET X, its digital route for submitting building plans to regulators. For projects using its three-gateway process, decisions shaping the design and client brief come before detailed construction requirements; simpler projects may use a separate Direct Submission Process. Developers and consultants therefore need to settle the route early and agree how their teams will hand over the information it requires.
Start with the project, not the portal
Since 1 October 2026, new projects with at least 5,000 square metres of gross floor area have had to use the CORENET X gateway process. That scope includes qualifying additions, extensions and major alterations, not only new buildings. Projects below the threshold can remain on CORENET 2.0 for now.
Some larger projects already in the approval process can also remain on CORENET 2.0. The deciding detail is whether the relevant formal submissions had begun there by 30 September 2026. A developer should establish that history with its consultants before the team plans the next submission. The BCA and URA circular sets out the scope and transition.
Give every discipline a place in the approval plan
For projects using CORENET X’s three-gateway route, the Design Gateway settles matters that shape the design and client brief. The Construction Gateway brings detailed requirements together before main structural works. The Completion Gateway covers as-built information for occupancy or completion approval. Simpler projects may instead use a separate Direct Submission Process.
That sequence gives the project team a practical planning task: decide which consultant will supply each required item, and when disciplines must check their information together. The three-gateway process explains the stages; the Code of Practice provides the detailed information requirements.
Check the filing before it goes in
For projects submitting digital building models, consultants should review the combined files before filing, resolve validation findings and check again. The official preparation checklist sets out the steps. A successful file export does not mean the whole submission is ready.
These checks prepare the filing; the agencies still decide whether to approve it.